(Deseret Morning News)
Deseret Morning News, Friday, December 08, 2006
Slow work on tailings worries Matheson
He says he doesn't want project to 'slip through the cracks'
By
Joe
Bauman
Deseret
Morning News
A Utah congressman wants to know why the U.S.
Department of Energy is taking so long to clean
up the Moab uranium mill
tailings.
"I just
want to make sure that
this project doesn't get delayed and really
just sort of slip through
the cracks," Rep. Jim Matheson, D-Utah, said
Thursday in a telephone
interview.
The
project, approved by
Congress, is to move the 16 tons of
radioactive uranium mill tailings
from their present site near the Colorado
River, north of Moab, to a
location near Grand Junction, Colo. They are
to be shipped the 30 miles
by rail car.
On Sept.
28, Matheson wrote to
Energy Secretary Samuel W. Bodman about
concerns that the agency was
not acting swiftly enough. On Nov. 29, Bodman
replied, saying a request
for task proposals was issued on Oct. 29, with
proposals due on Jan. 9,
2007.
"The
department believes the time
spent to develop the RTP (request for task
proposals) will pay
dividends in improved overall project cost,
schedule and protection of
the safety and health of the workers, public
and environment," Bodman
wrote.
"The
department is committed to completing this
project and returning the Moab site to an
environmentally sound
condition."
Bodman
added that the agency is
continuing to progress through actions like
completion of a network of
injection and extraction wells, which are
capturing and treating 100
gallons per minute of contaminated
groundwater. Also, it has cleaned up
41,000 cubic yards of contaminated soil
covering 28 acres along State
Route 191 north of Moab, he
added.
For the
2008 fiscal year, "we are
factoring in this project, along with other
cleanup priorities, as part
of our program planning and budgeting
process."
A
Matheson staff member noted
that the date when project proposals were due
to DOE had slipped from
Dec. 12 this year to Jan. 9,
2007.
Matheson
told the Deseret Morning
News he would like to know why the request for
contracts covered only a
fraction of the total cost and was to move
only part of the pile.
He said
the DOE "funding stream"
incorporated in the task order was for $102
million while the DOE has
acknowledged the total cost would be at least
$500 million. Also, the
work in the request is only to excavate 2.25
million tons, rather than
the full 16 million tons.
"The
department is committed to
making progress at Moab and by seeking a
contractor to build the
transport infrastructure and begin safely
moving the mill tailings, we
are another step closer to safe cleanup," said
DOE spokeswoman Megan
Barnett in agency headquarters, Washington,
D.C.
Matheson
was disappointed that the department did not
ask for a contract to remove all the
tailings.
"If the
DOE wants to outwait us, that isn't going to
happen," said Matheson, "because I'm not going
to leave this alone."
He said he does not know why DOE would set out a fraction of the project in the contract. If it were done by function — such as excavation cost or transportation cost — he could understand that, he said. "But I only see a dollar amount, and I see an amount of dirt that says 2.25 million tons, and the dirt is 16 million tons of material."
E-mail: bau@desnews.com